Find your permit agency and electric utility
Start with the property address and the name on your electric bill. For a property within the City of Los Angeles, the Los Angeles Department of Building and Safety (LADBS) handles the electrical permit. The utility handles the service connection and any meter-location review. Other cities in Los Angeles County and unincorporated areas can have different permit authorities. Use the address to confirm both before booking the work. LADBS electrical permits
LADBS lists like-for-like panel replacement as typically eligible for an express permit without plans. If you’re increasing service capacity or moving the meter, have the contractor confirm the route for the actual scope. Ask for the permit number and who will book the inspection. LADBS project and permit guide
Settle the meter location before pricing wall repairs
LADWP offers a residential meter-location review called a meter spot. A utility representative checks where the new service equipment can go and leaves a sketch for the job. If SCE serves the address, use its own project process for an existing-service upgrade and consult its meter-spot instructions. LADWP residential meter spot · SCE meter-spot instructions
A location change can affect how far wiring runs, where the wall opens, and whether work reaches a walkway or driveway. Ask the contractor to show the proposed position on a photo and explain what the estimate covers if the utility requires another spot. Compare the possible extra work using our LA panel upgrade cost guide.
Plan around project lead time and the power outage
RnR Electrician documented a City of LA overhead service upgrade from 100 to 200 amps for a homeowner planning an EV charger and mini-split. In that case, getting approvals and a utility appointment took much longer than the physical installation. Use the example to understand which steps can delay a project. Ask your contractor for dates based on your own scope and utility. RnR Electrician’s documented LA project
| Stage | Timing in RnR’s account | What to confirm for your project |
|---|---|---|
| LADWP meter-location review | About four weeks | Who files the request and how the utility’s decision is shared with the contractor. |
| Permit preparation and processing | About two weeks | The permit agency, application status, and whether a plan review is required. |
| Meter-lock and utility scheduling | About two weeks | Who books the utility appointment and when the outage date becomes firm. |
| Preparation and installation | One prep day and one installation day | The actual hours without power and whether restoration is expected that day. |
| Final inspection | Variable | When it will be requested, what sign-off is needed for reconnection, and who handles corrections. |
RnR reports same-day restoration in its example. LADWP also describes cases where meter installation follows the city’s approval of the service. Have the contractor confirm the inspection and reconnection sequence for your address. If anyone relies on powered medical equipment, discuss backup arrangements before agreeing to the outage window. Also plan how you’ll manage refrigeration, work equipment, and electric gates or garage doors. LADWP electric service FAQs
Keep the paperwork you’ll need after the upgrade
Ask for the finalized permit or inspection record, the itemized invoice, and any warranty terms that apply. Walk through the breaker labels and compare the finished wall with the patching and painting in your scope. If trenching affected paving or landscaping, check those areas too and put anything outstanding in writing.
If you’re applying for an EV outlet or panel rebate, ask your contractor how you’ll get the required photos, permit records, and invoice. Get the photos of the original equipment before it comes off the wall. SCE rebate documents and application paths
Discuss the permit and outage for your address
If you know your utility, tell us when you request a panel upgrade estimate. You can also review how Uni scopes permits, inspections, and wall restoration.
