Warehouse Demising Wall Removal in Pico Rivera

Warehouse storage aisle in Pico Rivera
Existing warehouse demising wall in Pico Rivera
Demising wall and adjacent aisle in Pico Rivera
Existing demising wall plan in Pico Rivera
Proposed demising wall removal plan in Pico Rivera

Project overview

Behind the project

Uni Construction prepared permit drawings for selective demising wall removal in an existing Pico Rivera warehouse. The drawings identify the sections to remove, the wall and building systems to retain, and the patching required at the floor and roof. The project is ongoing.

Scope of work

  • Document removal of the non-bearing demising wall between Suites A and B and a 150-foot section between Suites A and C.
  • Show the wall section between Suites B and C, the existing columns, and the existing electrical panel and wiring to remain.
  • Detail patching at the floor and roof where the walls are removed. The drawings show no change to use, occupancy, or floor area.

What the plans show

The existing and proposed drawings show which wall segments would be removed and which would remain. The 150-foot dimension applies to the section between Suites A and C.

Project at a glance

Location
8850 Rex Rd. Pico Rivera, CA 90660
Status
Ongoing
Added floor area
None
Partition removal
Suites A, B and C
Book a free consultation

Project FAQs

Which Pico Rivera warehouse partitions were marked for removal?

The drawings show removal of the non-bearing wall between Suites A and B and a 150 ft section between Suites A and C. The section between Suites B and C remains.

What stays in place during the warehouse wall removal?

The plans retain the existing columns, electrical panel, and wiring. They also show patching where the removed partitions meet the floor and roof.

Does the demising wall removal change the warehouse occupancy or floor area?

The permit drawings show no change to use, occupancy, or floor area. The scope is limited to the documented partition work.