Two-Bedroom Home Renovation Permit Design in La Habra

Residential exterior during the project in La Habra
Exposed framing during construction in La Habra
Side elevation during site work in La Habra
Proposed residential floor plan in La Habra
Residential exterior design views in La Habra

Project overview

Behind the project

Renovation work had started on this La Habra single-family home before a permit was in place. Uni Construction prepared the drawings, answered the city’s review comments, and helped the homeowner obtain a permit. The proposed layout shows two bedrooms, two bathrooms, a kitchen, a living room, and a front porch.

Scope of work

  • Prepare permit drawings for the renovation of an existing single-family dwelling.
  • Document the existing and proposed layouts, exterior elevations, and the structural details shown in the revised set.
  • Address the city’s architectural, structural, mechanical, electrical, and plumbing plan comments.

What the plans show

The cover sheet lists 880 sq ft of total covered area. The proposed floor plan shows two bedrooms and two bathrooms, along with a living room, kitchen, and front porch.

Project at a glance

Location
La Habra, CA
Total covered area
880 sq ft
Bedrooms
2 shown on plan
Bathrooms
2 shown on plan
Book a free consultation

Project FAQs

What does 880 sq ft mean on the La Habra renovation plans?

The cover sheet labels 880 sq ft as the total covered area. It is not presented as the amount of new space added by the renovation.

How did the proposed bathroom layout differ from the existing plan?

The existing plan labels one bathroom. The proposed plan shows two bathrooms alongside the two bedrooms.

Which plan review comments did the La Habra renovation address?

The revised set responds to architectural, structural, mechanical, electrical, and plumbing comments. It includes existing and proposed layouts, exterior elevations, and structural details.